| 
      
       1922 
       1922  
        Ms. Scripps and Harper invited Savage to determine the "practicality and feasibility of the accomplishment of a bathing pool for children in the Ocean at La Jolla, California."        1923 
       March 22, 1923 
         Mr. Savage submitted a report to Ms. Scripps. The report contained recommendations for constructing a bathing pool in the ocean in front of the location of the Casa de Mañana Hotel.        1930 
      May 1930  
        Ms. Scripps' representatives invited Mr. Savage’s “cooperation in the accomplishment of the projected splendid gratuity-bathing pool for children at La Jolla."  
      June 20, 1930  
        Ms. Scripps authorized construction of the pool as a gift to children. Savage's services on the project were also a gratuity to children. The next day, formal application was made to the War Department requesting permission to construct the breakwater feature of the pool.  
       June 21, 1930  
        Ellen Browning Scripps, through her Attorney in Pact, Dr. J. C. Harper wrote the Mayor and City Council of San Diego for permission to construct a "concrete breakwater in the Pacific Ocean at La Jolla." The stated purpose for the breakwater was to "create a Bathing Zone adjacent to the City of San Diego's La Jolla Park and City Streets."        June 26, 1930  
        Hydraulic engineer H. N. Savage (hereinafter. "Savage") also wrote the City (of San Diego (hereinafter "the City") on behalf of Ms. Scripps requesting permission to construct the breakwater. He enclosed with his letter plan drawings of the proposed breakwater. In this letter, Savage states the purpose of the breakwater "is to create a bathing pool" and the cost would be "in the vicinity of $50,000."  
       June 30, 1930  
        Permission from the City was granted. The City Park Department approved the construction on July 22, 1930. The War Department issued a construction permit on September 2, 1930.  
       September 15, 1930 
         With actual or tacit approvals in hand, Ms. Scripps awarded the construction contract to W.M. Ledbetter & Company. Two days later, equipment arrived on site and construction commenced. According to Savage, "([t]he purpose of the project was to create a safe bathing pool for children, sheltered from the ocean surf and winds." "The park area on the bluff adjoining the pool was improved by grading and the construction of parapet walls, and curbs. Shrubs have been planted and benches provided."  
      1931 
      June 1, 1931 
        Ms. Scripps gave the Children's Pool to the City of San Diego. 
      June 11, 1931 
        The Common Council of the City adopted Resolution 56609 whereby it ''express[ed] to this generous friend of humanity its most cordial thanks, on behalf of the children and citizens generally of the City of San Diego, for the unprecedented tidal bathing pool for the younger generation which has recently been constructed in ocean water on the shores of La Jolla, . . . ." 
      June 15, 1931 
        Governor of California signed Statute No. 937 of the laws of 1931, which granted to "the city of San Diego, ... all right, title and interest of the State of California, ... in and to all that portion of the tide and submerged lands bordering upon and situated below the ordinary high water mark of the Pacific ocean ……….. to be forever held by the city of San Diego and its successors in trust for the uses and purposes and upon the express conditions following, to wit: 
      (a) That said lands shall be devoted, exclusively to public park, bathing pool for children, parkway, highway, playground, and recreational purposes, and to such other uses as may be incident to, or convenient-for the full enjoyment of, such purposes;  
      (b) The absolute right to fish in the waters of the Pacific ocean over said tidelands or submerged lands, with the right of convenient access to said waters over said lands for said purpose is hereby reserved to the people of the State of California." 
      November 21, 1931 
        Operating Department of the City prepared a map depicting the land granted to the City by the State of California "for a swimming pool."       1933 
      1933 
        The Legislature passed and the Governor signed Statute No. 688 of the laws of 1933, that conveyed in trust all of the tidelands of the state bordering the City of San Diego. The more general grant of land described permissive uses of the tidelands, as contrasted with the 1931 grant, which provides for exclusive uses of the tidelands within the grant. Thereafter, for over sixty years, the Children's Pool remained open for the use and enjoyment of the people of San Diego and others.       1980 
      1980 and 1983 
        City of San Diego contracted for repairs to the Children's Pool breakwater. These repairs included replacing the handrail, improving lifeguard facilities and repairing the breakwater itself.  
      There is no evidence of any concern about or discussion of seals in the Children's Pool area until July, 1992. A representative of Sea World, Jim Antrim, discussed with Barbara Bamburger, a representative of "Friends of the Seals," the creation of a seal reserve in the vicinity of "the rock off Shell Beach (in front of 939 Coast Blvd)" as it was the "focal point of harbor seal activity concentrated between the months of January and, May."       1983 
      1980 and 1983 
        City of San Diego contracted for repairs to the Children's Pool breakwater. These repairs included replacing the handrail, improving lifeguard facilities and repairing the breakwater itself.  
      There is no evidence of any concern about or discussion of seals in the Children's Pool area until July, 1992. A representative of Sea World, Jim Antrim, discussed with Barbara Bamburger, a representative of "Friends of the Seals," the creation of a seal reserve in the vicinity of "the rock off Shell Beach (in front of 939 Coast Blvd)" as it was the "focal point of harbor seal activity concentrated between the months of January and, May." 
      December 20, 1983 
        City Manager advised the access ramp is erroded and needs to be upgraded to a concrete all-purpose ramp.  
          
      1992 
      November 25, 1992 
        A recommendation by the City Manager to essentially adopt the Park and Recreation Board recommendations, with the exception that the Seal Rock Reserve be established for a five-year period. The City Manager's recommendations were adopted. The water and land within the  reserve would be "off-limits to human and pet intrusion." In making these recommendations, the City recognized that marine mammal populations in the area of Seal Rock, and harbor seals in particular, had increased during the prior ten years.       
      1993 
      February 1, 1993 
        City Attorney approved a request recommending a reserve with a fixed boundary beginning 200 feet east of the seaward entrance to the Children's Pool. It passed unanimously after an amendment that extended the boundaries "to include the compromise area that goes practically to the beach that was presented by Barbara Bamburger. This discreet area shall be in effect for five years on a trial basis and is off limits to swimmers, divers and tourists. Access to the riptide is not affected because the divers can come in and go out through the Children's Pool." 
      October 25, 1993 
        Jane Sekelsky, Chief, Division of Land Management, State Lands Commission (hereinafter "SLC"), sent a letter to Carl Lind, a private citizen, copied to Robin Stribley, Natural Resources Manager, Park and Recreation District, City of San Diego. The letter concerned the creation of a marine mammal preserve within an area encompassed within a statutory trust grant. The SLC, on behalf of the State of California, expressed its concern that the Reserve may prohibit activities specifically reserved to the people of the State of California. Such activities include "the absolute right to the public use of said tidelands and to fish in the waters thereof, with the right of access to said waters over tidelands for said purpose." The Legislature has vested in the SLC: "All jurisdiction and authority remaining in the State as to tidelands and submerged lands as to which grants have been or may be made," and has given the commission exclusive administration and control of such lands. (Pub. Resources Code § 6301.) 
      November 15, 1993 
        SLC sends a clarifying letter addressed to Ms. Stribley and Barbara Bamburger. In which SLC more thoroughly advised the City of its rights and obligations in regard to lands over which it is the trustee. The State stated that "[t]he proposed ordinance is clearly inconsistent with the provisions of Chapter 937, Statutes of 1931. To ban public recreational uses as proposed would violate the specific provisions of the statute and the City's responsibility as Trustee." The court recognizes that the Reserve is situated within the broader tidelands grant of 1933 and not the much more narrowly and specifically worded grant of 1931. 
      That letter from the SLC placed the City on notice, as of November 1993, of its legal obligations under the 1931 statutory grant of public trust land. 
      November 18, 1993 
        California Coastal Commission approved the establishment of the Reserve in the vicinity of Seal Rock. The approval was conditioned on the City obtaining approval of the SLC and the boundaries of the Reserve not including any "sandy beach area."       1994 
      March 30, 1994 
        Fish and Game cautioned the City about interfering with "the public's right to fish in State waters." 
      July 25, 1994 
        City Council amended the ordinance establishing the Reserve to comply with the requirements of the Coastal Commission and to permit fishing pursuant to the request of Fish and Game.       1997 
      February 1997 
        City Manager updated Natural Resources on the Children's Pool closure. The report confirmed that the contamination was the result of "a seal excrement overload for Children's Pool." For fifteen years before 1994, the water quality in the Children's Pool met safe standards except on rare occasions. The report seemed to reasonably reject scaring away the seals from the beach or Pool, relocating them or physically preventing their entering Children's Pool. The "action plan" proposed was to discontinue placing barricades on the beach in the hope the seals will use the beach less if there were more human interaction and to hire a consultant to develop a plan for opening the sluiceways in the breakwater. It was believed the open sluiceways would increase the amount of water in the Pool and reduce the size of the beach. The increase in water would further dilute the concentration of feces in the water and a smaller beach might discourage some of the seals from hauling out at Children's Pool and thereby reduce the number of seals at the Pool. The Committee approved the Report recommending the hiring of a consultant in regard to re-opening the sluiceways. 
      October 1, 1997 
        Natural Resources and Culture Committee (hereinafter "Natural Resources") received an informational report from the City Manager about the "Closure of Children's Pool.” The report noted that the Pool had been closed to "water contact since September 4, 1997 due to continuously high fecal coliform counts." Obvious forms of contamination had been ruled out and it was believed that the source was harbor seal feces. This had riot yet been confirmed, but laboratory tests were being conducted. 
      The City Manager then discussed the City's lack of understanding of the reasons for "this unusual contamination level." The City did know that "[h]arbor seal populations have steadily increased off the west coast over recent years. This is evidenced at Children's Pool by an increased number of seals using the area." The City noted that a potential cause of the increase in the number of harbor seals at the Children's Pool was the nearby Reserve, which was three years into its five-year trial. Another potential cause was that "for the last year and a half, [City] lifeguards have erected barriers between seals hauled-out on the sand at Children's pool and the public." The barrier was to protect the public "from being bitten by a wild animal" or being fined for disturbing the seals. 
      The City Manager took the position that "[i]f the high contamination level both proves to be due to seals, and continues, it is the City's intent to find a solution which allows the peaceful co-existence of humans and seals at Children's Pool, to the extent the public health can be protected." He also recognized "[s]ince public health is potentially at risk, the federal Marine Mammal Act allows the City to take non-injurious actions which would reduce or eliminate seal usageof Children's Pool" 
      December 10, 1997 
        NMFS, an agency of the United States Department of Commerce, advised the City that "[w]hen Seal Rock was designated as a temporary reserve in 1994, a small number of harbor seals were utilizing the rock as a haul-out, while no animals were hauling out at Children's Pool Beach (CPB). According to [a] report, in 1996 the maximum number (62) of animals observed hauling out, on the rock occurred in April, while the maximum number (120) of animals observed hauling out at CPB occurred in June. Based on these data it appears that animals are preferring CPB over Seal Rock as their major haul-out site. This trend will most likely continue into the near future as the local seal population continues to increase in size." 
      NMFS also concluded that the seals at Children's Pool appear to be acclimating to humans and the effectiveness of the Reserve as a seal sanctuary is questionable. "Because, the harbor seal population both locally and statewide is healthy and increasing," removing Seal Rock as a Reserve will have no adverse effect on the seals.       1998 
      January 1998 
        Hubbs-Sea World Research Institute published a report of seal activity at the Reserve and Children's Pool. The report was based on photographs taken of each location every 30 minutes from November 1995 through September 1997. In most months, the peak count was significantly higher for the Children's Pool than the Reserve. 
      May 6, 1998 
         Natural Resources meets, with another report from the City Manager. 
      This time the City Manager recommended returning the barricades to separate the seals from the public. The removal of the barricades did not have the desired effect of reducing the seal population at the Pool. Also, complaints by public members of interactions between humans and seals were distracting the lifeguards from their public safety duties. For these reasons, the City Manager recommended the barricades be returned to the Pool. The report also concludes that re-opening the sluiceways was feasible, but three-quarters of the sand on the beach would need to be removed, in order to return the beachto its 1931 configuration. The City Manager recommended the sand removal. [ Id.] The Committee's action was to recommend that the City Council direct the City Manager to apply for a Coastal Development Permit to remove the sand and re-open the sluiceways. 
      August, 1998 
        The City was advised by the Center for Disease Control that seals can transmit diseases to humans. "Some seals can carry tuberculosis and Giardia. Fecal contaminant bacteria and viruses would also be a potential concern.” 
      December 22, 1998 
        The City requested authorization from the NMFS to remove sand from the beach. Dredging sand from the beach could constitute an "incidental harassment" of the seals. In justifying its request, the City represented that the breakwater was constructed to provide a sheltered swimming area for children; that the Pool has consistently been a popular attraction with a broad range of users who have come to rely on the Pool for beach recreation and water access; that skin and SCUBA divers depend on the Pool in order to safely enter and exit the water; that the beach behind the breakwater has gradually widened as sand accumulated in the Pool. By 1998, the shoreline at the Pool had advanced to near the end of the breakwater, at the mouth of the Pool. This resulted in very little protected area for recreational swimming. In addition, the swimming area had moved to within a close proximity to dangerous rip currents and their attendant safety concerns. Lifeguard rescues had increased because of this dangerous condition.  
      The City stated that it could restore the Pool as "a safe swimming area and [achieve] acceptable water quality [at] the Pool by reducing the beach width." The requested excavation would return the Pool to its early 1940's condition, with an enlarged area "available for recreational swimming and a safe region for the public to enjoy away from the dangerous rip currents."       1999 
      March 29, 1999 
        The recommendation of Natural Resources to remove sand from the Children's Pool came before the City Council which voted "to not dredge, not shoo the seals, instead put up a barrier to protect the humans from the seals and the seals from the humans and send it back to the Natural Resources Committee for an indepth (sic) review of all the issues including the legality and how it was left in the will." 1 Following the vote, the City withdrew its request for a coastal development permit from the California Coastal Commission. The next day, the rope barrier went up 
      August 4, 1999 
        Natural Resources considered the issue of letting the Reserve designation lapse. The City Manager, in his July 26 report, recommended letting the Reserve lapse as of its sunset date of September 16, 1999. 
      In his report, the City Manager discussed the potential impact on Children's Pool. He noted that the NMFS was considering whether to declare Children's Pool a "natural haul-out and rookery." Such a designation would impose a no-human-interference policy at the Children's Pool beach. NMFS had held off on such a designation because the City was pursuing a "shared-use-by-people-and-seals policy" and was working on a proposal to "address the pollution at the Pool by reducing the size of the beach and thus the available haul-out space for the seals." Since the City had "abandoned the shared use concept and did not pursue the project to address the pollution, (NMFSj assumes the City plans to maintain Children's Pool beach as a seals-only beach. Therefore, the Service believes the next logical step would be to manage Children's Pool beach as a permanent harbor seal haul-out and rookery." The net effect would be that the public could not use the beach set aside for the seals, nor could fishing occur in that area. 
      Natural Resources rejected the City Manager's recommendation and voted to recommend the Reserve be continued for another five-year term. On November 1, 1999, the City Council voted to make the Reserve permanent with a five-year review. 
      October 19, 1999 
        NMFS advised the City that it did not favor public beaches being closed to the general public due to harbor seals expanding their range and colonizing mainland beaches. Further, NMFS did not agree with a shared-use of Children's Pool by humans and seals. NMFS believed the City should decide if the Children's Pool is to be used by humans or seals, not both. 
      November 4, 1999 
        City Attorney wrote the SLC inquiring whether the SLC considered the closure of the Children's Pool, or usage of the Pool for viewing seals, a violation of the 1931 Grant of Public Trust over the area of the Children's Pool.       2000 
      February 2000 
        NMFS notified the City that it had decided to manage the Children's Pool as a harbor seal natural haulout and rookery. NMFS based this decision on their understanding that harbor seals first began hauling-out at Children's Pool in 1995, with ever increasing numbers and the fact that in 1999, for the first time, seal pup births were documented at the Pool. 
      March 15, 2000 
        Fish and Game advised the City that the City did not have the authority to create a seal reserve on public trust tidelands. Fish and Game cited several bases for this opinion, including violation of the State Constitution, preemption by Federal law and State law, and violation of the 1933 trust itself. 
      August 15, 2000 
        SLC responded to the City's request for an opinion. The SLC stood by their 1994 opinion that a small temporary seal reserve would not violate the 1933 trust and urged the City "to exercise its responsibilities in a flexible, balanced and thoughtful manner." However, the SLCdid not address the City's inquiry concerning seals at the Children's Pool.       2003 
      February 11, 2003 
        NMFS advised the City that it could not intentionally harass the seals at Children's Pool in order to remove them. However, it could undertake activities that might temporarily displace the seals. An example would be a dredging project intended to improve the water quality at Children's Pool. 
      March 13, 2003 
        California Coastal Commission advised the City that the rope barrier the City had erected closing off most of the beach at Children's Pool and access to the water at the Pool, needed a Coastal Permit. The Commission was concerned that a supposed temporary situation had been in place for four years and appeared to be permanent. 
      March 21, 2003 
        County of San Diego informed the City that with the adoption of AB 411 by the Legislature, the status of the Children's Pool had changed from "closed" to "advisory", since the water contamination was not due to a sewage spill. 
      April 1, 2003 
        The City Council considered the request of the Coastal Commission to modify the permanent status of the Reserve. The City Manager recommended that the City accept the permit with the special conditions. The City Council declined to follow the recommendation and did not accept the coastal permit with its special conditions. The Council directed that the signage and the docent program continue and further directed the City Manager to make a presentation before California's Marine Life Protection Working Group, seeking advice on the "appropriate status for the area." Also, the City Manager was directed to once again return to Natural Resources with a report on "how, in compliance with federal law, to reduce pollution levels and to return the Children's Pool to recreational use for children." 
      July 29, 2003 
        the Children's Pool Technical Advisory Committee met to discuss ways to Accomplish the directive of the City Council, for an unpolluted Children's Pool and a joint use of the beach at the Pool. The members of the Committee included, representatives from the NMFS, Coastal Commission, Fish and Game, County Environmental Health, Hubbs-Sea World, Park and Recreation, lifeguards and other City representatives. They went over most of the proposed "solutions" that had been enumerated over the years. They concluded the most viable options were "I. Dredge the beach in conjunction with floating platforms; 2. Close beach to public use; and 3. Create a new Children's Pool and leave current Children's Pool for seal use."       2004 
      June 17, 2004 
        City Manager provided Natural Resources with another report on seals at Children's Pool. This report laid out a comprehensive plan for restoring the Children's Pool to an unpolluted and safe condition. The plan was centered on dredging a substantial portion of the sand at the Pool. It was believed this would restore the water quality in the Pool to an acceptable level and relocate the water in the Pool further into the breakwater area away from the open sea and dangerous rip currents. The estimated cost of dredging the Pool ranged from $250,000 to $500,000. Another $50,000 would need to be budgeted annually to pay for anticipated dredging every three to five years. 
      June 23, 2004 
      Natural Resources considered the recommendations of the City Manager. The Committee voted to refer the matter to the full City Council "with no recommendation." 
      On or about August 13, 2004 
      The City posted new signsat the Pool explaining that the rope was a "guideline to avoid disturbing the seals" and that swimming was "not recommended" because of excessive bacteria levels. 
      September 14, 2004 
      City Council once again held hearings on the Children's Pool. Addressing the Council that day was James Lecky of the NMFS. He advised the Council that harbor seals are a healthy species which are growing in population and not in anyway endangered or threatened as a species. In fact, as the population of harbor seals expands "[t]hey are causing problems ... up. and down the coast in terms of invading harbors, causing property damage and limiting access to beaches that are important for other " public uses." He then told the Council: "The tools that are available to the City and other local governments agencies really reside in [Marine Mammal Protection Act] §109(h)." He said "animals can be moved out of an area if they are either presenting a public nuisance or they're causing a public health hazard." It was his position that the seals at Children's Pool were a local issue for the City to resolve. At the end of the meeting, the Council voted "to design and permit the sand removal project and open the pool for year-round use. Direct that the opening of the sluiceways in the Children's Pool be evaluated as an alternative method to obtain the sand removal and tidal flushing as part of this effort. Direct that the rope barriers and sign posts be immediately removed to restore public access to the area and that new signs be placed."       2005 
      Aug 25, 2005 
      Superior Court William C. Pate rules against the city in a lawsuit brought by a private citizen contending the City had abandoned its fiduciary duties regarding the trust by which it received Children’s pool and the breakwater. The city is directed to carry out the dredging of accumulated sand and restore the area to match photos of its condition in 1941, the earliest photos available. Tentative statement 
          The City mounts an appeal and the order is stayed 
      Oct 17, 2005 
      NOAA SouthWest Regional Admnistrator Rodney McInnis wrote to our City Attorney assuring the City could move seals off Childrein's Pool beach prior to removing the excess sand, without a permit.  
      
      April  5, 2006 
        NR&C committee Chaired by Donna  Frye.  In spite of court order, approves  a motion to reinstate the rope barrier from January1 to May 1, forever.   To be presented on April 17, 2006 to the  City Council. Item 11.     Reading of 3/26 letter from NOAA, Don  Masters.  Video time 0:31 to 1:09.  
        Natural  Resources and Culture Committee Meeting Actions 
      April  17, 2006 
        City Council:  Barrier placement approved Jan 1 to May 1.  Letter from Masters read.  Approved by all districts except La Jolla. Meeting  Minutes 
      April  18, 2006 
        City Council, ITEM-105 Declaring the rope barrier at the Children’s  Pool beach will be reinstated for the remainder of this year’s pupping season  and will be placed at the beach from January 1 through May 1 every year from  this point forward. Per letter from Donald W. Masters’ dated 3/21/2006..  Meeting Minutes
 
      March 21, 2006 
        Don Masters, of NOAA Office of Law Enforcement in a letter to our Mayor, expresses his department's concern with Shared Use promting complaints to his office and the NOAA hotline. He recommends and supports a one time closure of the beach through April, or reinstating the advisory rope barrier.  He notes his department does not have the resources to patrol the beach. 
       
      Nov  15, 2006 
        NR&C Committed recommends pupping season rope be  Dec 15 to May 15. To protect unborn pups in December and newborn pups in  May. No opposition groups advised to attend.
       
      Dec  5, 2006 
        City Council changes pupping season  from Jan1 – May 1 to Dec 15 to May 15 effective immediately. Meeting Minutes 
      Dec 11, 2006 
        Don Masters, of NOAA Office of Law Enforcement in a letter to our City Attorney, expresses his department's concern with Shared Use promting complaints to his office and the NOAA hotline. He recommends and supports the City closing or placing the advisory rope barrier to prevent possible violations of the MMPA. 
       
      2007 
      Jan  24, 2007 
        The appeal continues. The City  applies to put up a rope across Children’s Pool again on an emergency  basis.   A hearing officer directs the  permit to require public hearing before a community planning association.   The permit states throughout it that the  rope is "not intended to limit public access to the beach".  
      Feb  21, 2007 
        Natural Resources and Culture  Committee proposes an ordinances to outlaw beach fires and to protect  seals.  Sweeping ordinance is sent back  to committee to die by Homeland Security chief Jill Olen,  Natural  Resources and Culture Committee Meeting Actions 
      June  20, 2007 
        On  advice from City Attorney, NR&C Committee votes to forward an item to the  full City Council for 
        consideration,  and direct the applicant, Park and Recreation Department, to add the nighttime  rope to their existing application for a permanent rope barrier during pupping  season, from December 15 through May 15. 
  Natural Resources  and Culture Committee Meeting - Revised   
Sept 10,2007 
   A 3 judge appeal panel unanimously rejected every argument the City Attorney had presented, and let stand Pate's orignal decision.  
Nov 30, 2007 
  Don Masters, of NOAA Office of Law Enforcement in a letter to our City Attorney, expresses his department's concern with complaints to his office and the NOAA hotline. He recommends and supports the City closing or placing the advisory rope barrier to prevent possible violations of the MMPA.  He points out the MMPA covers "in waters or on lands under the jurisdiction of the United States", perhaps doubtful he has jurisdiction to take preemptive measures on State Land like the Children's Pool. 
 
      
      Jan  3, 2008 
        An emergency permit is not feasible,  so City tries for normal rope barrier permit.    La Jolla Community Plannning Association denies the permit 7-2.    Next day Superior court rules rope barrier  illegal. 
              Mar 19, 2008 
        City Attorney issues declaration  for emergency rope barrier permit, precluding CCC approval. 
              April 29, 2008 
        Citizen files appeal with CCC of  emergency rope barrier permit issued by City for itself 
              June 12, 2008 
        Appeal of emergency rope barrier  denied by Development Services on its own authority 
      Jan  7, 2009 
        City Council votes in closed session 6-1 to advance the  proposal to amend the 1931 Tidelands Trust to open session 
      Jan  9, 2009 
        Report from the City Attorney to Mayor  and City Council.   
         
        Jan  26, 2009 
        Lawsuits  against the City for starting to comply with the O’Sullivan court order from  APRL. Meeting Minutes  
        The  Council heard public comment on this issue and came back later with a related  Closed Session item.   Closed Session Docket 
      Feb  17, 2009 
        Jan Goldsmith introduces motion to  amend the trust to allow the City discretion to allow marine mammals at  Children’s Pool.  Meeting Minutes 
        Later Pease claims publically it was his idea,  apparently part of a settlement. 
      May  17, 2009 
        DFG approves San Diego’s EIR to  carry out the Pate decision court order. 
      June  9, 2009 
        City Council.  Cost estimates for removing seals by playing  recordings of dogs by a City employee with an assigned guard. Reports entered  that seals cannot be frightened and would only spread out at best.  City Attorney promised his trust amendment  will solve it all.  Tuesday Supplemental 1 Docket      
      Sept  22, 2009 
        Against staff recommendations and  La Jolla Community recommendation, City Council votes to not accept the EIR for  sand and seal removal required by Pate and Hoffman’s court order. Tuesday Minutes 
      Nov 5, 2009 
        La Jolla Community Planning  Association rejects rope barrier permit application as encroachment on vertical  access. 
      Dec 2, 2009 
        City Hearing Officer approved CDP  701673 & SDP 701765 for annual placement of the rope barrier during pupping  season, December 15 to May 15. That permit approval was appealed to the Planning  Commission but denied.  Appealed then to  the Coastal Commission by a citizen.  
       Dec 17  2009 
        City Attorney has rope barrier  installed on the beach, ignoring appeal filed to CCC. 
Feb  12, 2010  
  Coastal Commission     Citizens had petitioned the CCC for relief  from harassment and access curtailment by activists.   The Director concedes “the issue of public  access and impedance of public access is clearly an issue within our  jurisdiction”.   The Commission requests  he send a “letter of concern” to the City and “all the right entities so that  the net is spread far and wide”.    The  director replied “OK, no problem.”    It  never happened. video archives minute 30:30 
March 17, 2010 
  NR&C committee considers several ways to prohibit public  access to the Children’s Pool.  
Natural  Resources and Culture Committee Meeting - Revised 
April  5, 2010 
  NR&C committee considers  several ways to prohibit public access to the Children’s Pool. 
    Natural  Resources and Culture Committee Actions    
  Natural Resources  and Culture Committee Meeting - Special 
May  17, 2010 
  Special City council session to  vote on motion by Frye close CP by ordinance Dec 15 to May 15 and leave the  rope in place the rest of the year.   Lightner adds banning dogs and accepting a ranger. Directs Mayor to seek  emergency rope permit.  Directed staff to  recommend whether pupping season dates need to be altered.   Assigns City Attorney to the deails.  Monday Minutes 
May 18, 2010 
  Donna Frye received a letter from the regional director of NOAA McInnis, just a day late. He expressed recommendation for her proposals to close or cordon off the beach.  Later he ascribed authorship of the letter to his  staff, he signing it in support of them.  
June  16, 2010 
  City Attorney reports to NR&C  Committee on adding to ordinance 63.0102 to prohibit access to Children’s Pool  Dec 15 to May 15 and dogs at all times.   CA memorandum 6/10/2010.  Natural  Resources and Culture Committee Meeting Actions 
Sept 15, 2010 
  Hearing Officer approved placement  and maintenance of a year-round rope barrier at Children's Pool in perpetuity. To  go to Planning Commission.  CDP 701673,  SDP 701765  
Sept 24, 2010 
  La  Jolla Community Planning Association appealed the Hearing Officer's approval of  the year-round rope to the Planning Commission. 
Nov 9, 2010 
  Park and Recreation advises Coastal  Commission local staff they have no technical studies on the effectiveness of  the rope barrier.  Staff is reminded the  rope does not prohibit access but Park and Rec objects to signs revealing that  fact. 
Dec  9, 2010 
  Planning Commission hears appeal by  La Jolla Community Planning Association of year round rope permit. Rules unanimously  the year round rope would be an  encroachment on access incompatible with the Local Coastal Plan. 
June  23, 2011 
  Judge Lisa Foster lets the TRO from  May 15 lapse and the rope drops pending outcome of lawsuit. 
  “Foster remarked on a  video of the recent 80th anniversary celebration of the dedication of  Children’s Pool, in which seals were in close proximity to people on the beach  but didn’t flush. 
  “Where is the irreparable harm?” Foster queried. 
July  15, 2011 
  Judge Lisa Foster requires the  Planning Commission reconsider its ruling that the year round rope would be an  encroachment on access incompatible with the Local Coastal Plan. 
Aug 4, 2011 
  Planning Commission meets in closed  session with City Attorney, George Schaefer, to discuss litigation: APRL v.  City of SD, Case   37-2011-00085228-CU-WM-CTL. Plaintiffs challenged the PC's denial of the  City's Park and Recreation Department's application for a CDP and SDP to  install a year-round guideline rope barrier to protect seals at Children's  Pool. The Superior Court remanded the case back to the PC for further  deliberation. 
  
  Sept 29, 2011 
  City Attorney requests CCC consider  Children's Pool beach as all historic tidelands.  Local staff agrees, assumes jurisdiction.  
 
  Nov 9, 2011 
  Local Coastal Commission staff  requests Park and Recreation technical analysis supporting the need for a year  round rope barrier.  Asks how public  access will be assured, requests an analysis of alternatives.   Received none. 
Jan  30, 2012 
City Council Closed Session  In two of these cases, Plaintiffs APRL &  Friends of the Seals filed lawsuits against the City or Mayor seeking  court-ordered installation of a rope barrier at the La Jolla Children’s Pool  for the purpose of protecting harbor seals from humans.  In a third case,  Plaintiffs are seeking court-ordered closure of the Children’s Pool to the  public during the harbor seal pupping season. Closed Session Docket 
July  11, 2012 
  Coastal Commission gives unanimous  though reluctant pre-approval of a year round rope permit.  Requires 3 year term and City pays all legal  costs of the Commission for doing it.  
Sept  27, 2012 
  The Planning Commission re-considers  the appeal by the La Jolla Community Planning Association per court order.   It again unanimously upholds the appeal and  the year round rope permit is stopped again 
Dec 3, 2012 
  City applies for Federal permit to  rebuild the Children's Pool lifeguard tower, submitting scientific evidence the  seals will not be disturbed by heavy equipment.   New seals expected to habituate and not react to humans in a few days. 
  Dec 13. 2012 
  Local Coastal Commission staff  reiterates advice not to invoke an ESHA at Children's Pool as part of an LCP  amendment.  Cites concern for public  access and divers, beachgoers and swimmers but new internal discussions of  resources led local staff to be supportive of full seasonal closure to the  public. 
. Dec  15, 2012 
  Mayor Filner promises to lengthen  the CP rope to 152’ and get it made year round before May 15, as well as push  through the winter closure barricade. 
 Dec  21, 2012 
  Filnner changes the permit and has  it recorded with total disregard for the law.   Directs the rope be lengthened to his liking.   The opening is now 3’ and no longer looks  like an opening and cannot be seen from the sidewalk. The local Coastal  Commission office does not act. 
 Dec  24, 2012 
  City Attorney issues  memorandum.  Moving the rope was illegal and dangerous and  required a complete new permit process. Mayor Filner ignored him..  
Jan 23,  2013 
  La Jolla Community Planning  Association writes letter to Mayor opposing lengthening the rope barrier and  any curtailment of public access.  
Jan 31, 2013 
  Mayor filner installs 24 hour  surveillance camera at Chldren's Pool, donated by Sara Wan. Permit allows only  research uses.   No research was ever  done. 
March 18, 2013 
  Mayor Filner declares an emergency  permit to close the beach at night, without notifying the CCC.   Local CCCstaff issued an after-the fact  permit granted as de minimus April 10 in Santa Barbara to make it all right.    
April  19, 2013 
  Lawsuit by FoCP for Filner’s  changing the rope length on Dec 21.  Judge  finds "It appears to the Court that the City violated the Coastal Act and  Land Development Code by unilaterally installing a 152 foot rope barrier  without a Coastal or Site Development Permit".   No action required by court.  
May 14,  2013 
  Mayor directs police, ranger and  lifeguards to cite or arrest anyone forward of the advisory rope barrier if a  seal moves, assuming that movement was a resulting wildlife disturbance.   Neither harm nor intent are required.   CCC not consulted. 
May 23, 2013 
  Development  Services. Application filed with the City of San Diego for a standard Coastal  Development Permit (CDP) (Process 3) following the Emergency CDP under PTS  316719 for closure of the Children’s Pool from sunset to sunrise effective  through May 15, 2013 at the La Jolla Children's Pool. 
June 18, 2013 
Night beach closure by  Mayor Filner fails in court.  Visitor on  the beach found not guilty because order was issued without Coastal Permit in  March.   
July 9, 2013 
  Mayor agrees to allocate $50,000 to  Wan Conservancy for expenses of Children's Pool surveillance camera.   Wan offers to maintain the camera for  $283,000/year.  Neither happened.   
Sept  12, 2013 
  Planning Commission approved  Resolution 4545-PC recommending to the City Council "approval and adoption  of the Community Plan/Local Coastal Program (CP/LCP) Amendment, Ordinance and  Negative Declaration No. 225045." 
Oct  25, 2013 
  Local Coastal Commission staff advises  the City they do not support an ESHA designation as part of closure of Children's  Pool by LCP amendment.  Local staff  supplies the exact text the City may use to effect closure through section 30230.   
Oct  29, 2013 
  City Council cancels hearing on  ESHA based Pool closure permit application. Resolution R-2014-198: Adopted negative declaration and closure  ordinance and return to staff. Tuesday Minutes   
 
Nov 9, 2013 
  City announces fence preventing  public access to rocks above La Jolla Cove can be climbed over any time, hoping  persons doing so will cause sea lions to leave area 
. 
  Dec 12, 2013 
  PC makes recommendations to the  City on Children's Pool, vote 4-3. Confusion of meaning of vote leads to  re-vote in Janurary 16, 2014 where it passed 4-3 
 
  Dec 13. 2013 
  A fence preventing access to upper  rocks above La Jolla Cove has a gate installed in hopes people will cause sea  lions to vacate the area.  A law suit to  remove the fence completely noted there had never been a coastal permit for the  fence. 
 
  Dec 15. 2013 
Mayor announces intended tripling  of City Ranger hours at the beach.    Funding was not allotted.   
Jan 2, 2014 
  City Council and Coastal Commission received a letter from NMFS Director of Protected Resources." ...the most preferable outcome is one of shared use - where the MMPA is complied with but no unnecessary restrictions are placed on other beach or ocean users" and  "...review the pre-emption provisions ofMMPA Section 109 (a), 16 U.S. Code Section  1379(a)"  
Feb 4,  2014 
  Local Coastal Commission staff states police action  curtailing beach access not found in the LCP does not require CCC review.  Also violation of State land grants are not  in the LCP and do not require CCC review.    
Feb  24, 2014 
  City Council Resolution confirms  CEQA Neg Declaration Declaration 225045 allowing LCP Plan amendment to close the beach seasonally. Monday Minutes   Item  201 
March  11, 2014 
  City Council adopts City ordinance  amendment to prohibit beach access 12/15 to 5/15 every year. Tuesday Minutes  /   ITEM-51:   La Jolla Childrens’ Pool Beach  Seasonal Closure, Project No. 225045.  (La Jolla Community Plan  Area.  District 1.) 
June 13th, 2014 
  NMFS clarified in a letter "...In general terms, Section 109 (a) prohibits enforcement of laws or regulations relating  to the taking of marine mammals except by a state to which the Secretary of Commerce or the  Secretary of the Interior has transferred authority for the conservation and management of the  spec1es. That authority has not been transferred to the City" (Letter) 
August 14, 2014 
  Coastal Commission gives San Diego permit to close the Children's Pool Dec 15 to May 15 for 5 years. 
With conditionThe City is to consider  ways to clean the sand and water (open sluiceways) and install an ADA ramp to the sand. VIDEO The City seems  prepared to comply, though not promising.  
October 10, 2014 
  Friends of the Children's Pool petitioned in Superior Court for a writ of mandate against San Diego and the Coastal Commission. Violations of the State Constittution, the 1931 Trust and the Coastal Act were cited. 
  |